PRINCE2 Foundation — Question 306
How should the ‘progress’ practice be used?
Answer options
- A. To define how the products will be delivered to enable control
- B. To predict whether the benefits will exceed the costs
- C. To identify opportunities that may make the project more successful
- D. To deliver change which will benefit people in their day-to-day work
Correct answer: A
Explanation
The correct answer is A because the 'progress' practice is primarily concerned with establishing the delivery framework for products, which allows for effective oversight and management. Options B, C, and D, while relevant to project management, do not specifically address the purpose of the 'progress' practice in terms of delivery control.