PRINCE2 Foundation — Question 305

The project manager needs to document how risk management will be undertaken during the project.

In which step of the ‘risk management’ technique should the project manager document this?

Answer options

Correct answer: A

Explanation

The correct answer is A because documenting how risk management will be executed aligns with defining the context and objectives of the project. The other options focus on identifying or assessing risks rather than documenting the management approach.