PRINCE2 Foundation — Question 312
Which is NOT one of the PRINCE2 integrated elements?
Answer options
- A. Tailoring PRINCE2 to the project environment
- B. The processes
- C. The products
- D. The themes
Correct answer: C
Explanation
The correct answer is C, as 'the products' are indeed one of the integrated elements of PRINCE2. Options A, B, and D each represent components that are integral to the PRINCE2 methodology, including tailoring, processes, and themes.