PRINCE2 Foundation — Question 299

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project
2. To provide the required authority to initiate the project
3. To plan the work required for project initiation
4. To provide business justification for initiating the project

Answer options

Correct answer: C

Explanation

The correct answer is C, as the objectives of the 'starting up a project' process include planning the work needed for project initiation and ensuring there is business justification for starting the project. Options A and D are incorrect because they focus on aspects related to corporate interface and project authority, which are not primary goals of this process.