PRINCE2 Foundation — Question 298

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

Answer options

Correct answer: A

Explanation

The Benefits management approach is essential for tracking and confirming that the expected benefits have been delivered. The Business case outlines the rationale for the project, while the Quality management approach focuses on ensuring project deliverables meet quality standards. The End project report summarizes the project outcomes but does not specifically plan for measuring improvements.