PRINCE2 Foundation — Question 300
When is a work breakdown structure MOST useful?
Answer options
- A. When there are multiple work packages with a mix of internal and external resources
- B. In a simple project with one work package for the work of a small team
- C. When establishing a change authority aligned to project tolerances
- D. When assuring business, user and supplier aspects of project performance
Correct answer: A
Explanation
The correct answer is A because a work breakdown structure is most beneficial in complex projects involving multiple components and diverse resource allocations. The other options suggest simpler scenarios where a work breakdown structure may not be necessary, such as projects with only one work package or those focused on authority and performance aspects.