PRINCE2 Foundation — Question 271
What process provides information on a team's work to the project manager?
Answer options
- A. Controlling a stage
- B. Directing a project
- C. Managing a stage boundary
- D. Managing product delivery
Correct answer: D
Explanation
The correct answer is D, Managing product delivery, as it focuses on ensuring that the project's products are delivered as planned and includes reporting progress to the project manager. Options A, B, and C pertain to different aspects of project management that do not specifically emphasize the reporting of a team's work to the project manager.