PRINCE2 Foundation — Question 271

What process provides information on a team's work to the project manager?

Answer options

Correct answer: D

Explanation

The correct answer is D, Managing product delivery, as it focuses on ensuring that the project's products are delivered as planned and includes reporting progress to the project manager. Options A, B, and C pertain to different aspects of project management that do not specifically emphasize the reporting of a team's work to the project manager.