PRINCE2 Foundation — Question 272
Which is an objective of the 'managing a stage boundary' process?
Answer options
- A. To manage risks and issues that may impact the current stage
- B. To prepare an exception plan as directed by the project board
- C. To define how and when all the project's products will be delivered and at what cost
- D. To control the delivery of the project's products
Correct answer: B
Explanation
The correct answer is B because managing a stage boundary involves preparing an exception plan when there are deviations from the plan, as per the project board's direction. Options A, C, and D do not specifically pertain to the objectives of managing a stage boundary, focusing instead on risk management, product delivery planning, and control, respectively.