PRINCE2 Foundation — Question 270

During the 'initiating a project' process, who specifies the required level of management control?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Project board, as they are responsible for defining the governance and oversight required for the project. The other options, such as the Project manager and Project assurance, have roles in executing and ensuring project quality but do not set the level of management control.