PRINCE2 Foundation — Question 269
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.
Answer options
- A. benefits, change, risk,
- B. benefits, quality, risk,
- C. change, quality, risk,
- D. benefits, change, quality,
Correct answer: B
Explanation
The correct answer is B because 'benefits, quality, risk' are key aspects that align with project performance management. The other options include terms that do not fully encompass the necessary elements for effective project oversight.