As a minimum requirement for applying the risk theme, what must specifically be assessed?
Answer options
- A. Whether a risk may cause the project to exceed its cost tolerance
- B. Whether a risk may affect the project-level quality tolerances
- C. Whether a risk may impact the underlying technical assumptions
- D. Whether a risk may alter the project's business justification
Correct answer: D
Explanation
The correct answer is D because assessing whether a risk alters the project's business justification is crucial for understanding its overall value and viability. The other options, while important, focus on specific project metrics rather than the broader justification for the project's existence.