Which is an objective of the 'directing a project' process?
Answer options
- A. To review and approve a project mandate
- B. To ensure corporate or programme management has an interface to the project
- C. To define how risks, issues and changes will be managed
- D. To obtain approval for completed products
Correct answer: B
Explanation
The correct answer, B, is focused on ensuring that there is a communication link between the project and higher management, which is crucial for project alignment with organizational goals. Options A, C, and D, while relevant to project management, do not specifically address the oversight and communication role of the directing process.