What is an advantage of dividing the project into stages?
Answer options
- A. Detailed plans can be prepared closer to the time events will take place
- B. the project board can delegate management of the project to team managers
- C. The project can be authorized by the project manager on a stage by stage basis
- D. The project brief can be updated towards the end of each stage
Correct answer: A
Explanation
Option A is correct because dividing the project into stages allows for more precise planning as the details become clearer closer to execution. Options B, C, and D, while relevant to project management, do not specifically address the immediate benefit of planning details closer to the event timing.