The project manager needs to define key information so that the project board can decide whether to proceed with planning the project in more detail.

Answer options

Correct answer: A

Explanation

The correct answer is A, as 'Starting up a project' involves defining key information to enable the project board to decide on the project's feasibility. Option B, 'Initiating a project,' refers to the phase that follows this decision, while options C and D relate to different aspects of project governance and management that occur later in the project lifecycle.