The team manager has organized a workshop with project stakeholders to define the detailed requirements for a number of outputs.
Which principle is being applied by the team manager as part of the ‘people’ element when holding this workshop?
Answer options
- A. Focus on products
- B. Tailor to suit the project
- C. Define roles, responsibilities and relationships
- D. Ensure continued business justification
Correct answer: A
Explanation
The correct answer is A, as focusing on products emphasizes the importance of understanding and defining the outputs that stakeholders require. Options B, C, and D, while relevant to project management, do not directly relate to the act of defining detailed requirements in a workshop setting.