PRINCE2 Foundation — Question 251
Which should be funded from a change budget?
Answer options
- A. The Starting up a Project process
- B. A fallback plan
- C. An agreed change to the scope of a project
- D. A change to a plan, within allocated tolerances, due to poor estimating
Correct answer: C
Explanation
Option C is correct because it refers to a confirmed change to the project's scope, which necessitates funding from the change budget. Options A and B do not involve changes to the project scope and are generally covered by different budgets. Option D describes a change within tolerances due to poor estimation, which typically would not require a change budget.