PRINCE2 Foundation — Question 251

Which should be funded from a change budget?

Answer options

Correct answer: C

Explanation

Option C is correct because it refers to a confirmed change to the project's scope, which necessitates funding from the change budget. Options A and B do not involve changes to the project scope and are generally covered by different budgets. Option D describes a change within tolerances due to poor estimation, which typically would not require a change budget.