PRINCE2 Foundation — Question 252
Before the initiation stage, which product would define how management products are approved?
Answer options
- A. Communication management approach
- B. Quality management approach
- C. Project plan
- D. Initiation stage plan
Correct answer: B
Explanation
The correct answer is B, as the Quality management approach outlines the standards and processes for ensuring quality in project management, including the approval of management products. The other options, while relevant to project management, do not specifically address the approval criteria for management products before the initiation stage.