PRINCE2 Foundation — Question 250

Which management level should approve a course of action if project-level tolerance is exceeded?

Answer options

Correct answer: B

Explanation

The Project board is the correct answer as they are accountable for making decisions regarding the project when it exceeds established tolerances. The other options, such as the Project manager and Team manager, typically have limited authority and may require escalation to the Project board for significant issues.