PRINCE2 Foundation — Question 250
Which management level should approve a course of action if project-level tolerance is exceeded?
Answer options
- A. Corporate, programme management or the customer
- B. Project board
- C. Project manager
- D. Team manager
Correct answer: B
Explanation
The Project board is the correct answer as they are accountable for making decisions regarding the project when it exceeds established tolerances. The other options, such as the Project manager and Team manager, typically have limited authority and may require escalation to the Project board for significant issues.