PRINCE2 Foundation — Question 23
What is a goal of the 'implement' step within the recommended risk management procedure?
Answer options
- A. To prepare specific management responses to identified risks
- B. To monitor the effectiveness of actioned risk responses
- C. To estimate the risk to the project in terms of probability and impact
- D. To communicate information related to the risks faced by the project
Correct answer: B
Explanation
The correct answer is B because the 'implement' step focuses on evaluating how effective the risk responses are after they have been executed. Options A, C, and D refer to different phases in the risk management process, such as preparing responses, estimating risks, and communicating risks, which are not the primary goal of the implementation phase.