PRINCE2 Foundation — Question 22

Which is a minimum requirement for applying the business case theme?

Answer options

Correct answer: C

Explanation

The correct answer is C because it emphasizes the necessity of defining actions to ensure that the benefits of the project are realized. Options A and B relate to reporting and evaluation but do not address the proactive aspect of confirming benefits. Option D focuses on monitoring changes, which is not specifically linked to applying the business case theme.