PRINCE2 Foundation — Question 22
Which is a minimum requirement for applying the business case theme?
Answer options
- A. To provide statements of actual benefits at benefits reviews
- B. To report on project performance at project closure
- C. To define the actions required to confirm the project's benefits are realized
- D. To monitor changes to the project plan to identify exceptions
Correct answer: C
Explanation
The correct answer is C because it emphasizes the necessity of defining actions to ensure that the benefits of the project are realized. Options A and B relate to reporting and evaluation but do not address the proactive aspect of confirming benefits. Option D focuses on monitoring changes, which is not specifically linked to applying the business case theme.