PRINCE2 Foundation — Question 21
Which is an objective of the 'initiating a project' process?
Answer options
- A. To ensure that baselines are established and controlled
- B. To ensure that the business case is kept under review
- C. To ensure that the planned products are delivered within tolerances
- D. To ensure that user acceptance of the products is confirmed
Correct answer: A
Explanation
The correct answer is A because the initiating a project process focuses on setting the foundation for the project, including establishing baselines. Options B, C, and D pertain to other phases of project management, such as ongoing review and delivery, rather than the initial phase.