PRINCE2 Foundation — Question 20

Which is a purpose of the 'initiating a project' process?

Answer options

Correct answer: D

Explanation

The correct answer is D because the 'initiating a project' process focuses on understanding the necessary work to deliver project outcomes. Option A relates to stage planning, which is not the primary focus at this stage. Option B is about decision-making but not the understanding of work required, and option C pertains to acceptance rather than initiation.