PRINCE2 Foundation — Question 24
What should the benefits management approach define?
Answer options
- A. What actions will be taken to ensure the project's outcomes are achieved
- B. What will be used to record the effectiveness of the project's approaches
- C. How the project has progressed against its plans
- D. The suitability of the project management team structure
Correct answer: A
Explanation
The correct answer is A, as the benefits management approach specifically focuses on the actions required to achieve the desired outcomes of the project. Options B and C relate to recording and assessing effectiveness and progress, respectively, while option D concerns the organizational structure of the management team, which is not directly tied to benefits management.