What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
Answer options
- A. Configuration Item Record
- B. Quality Register
- C. Highlight Report
- D. Checkpoint Report
Correct answer: D
Explanation
The Checkpoint Report provides detailed updates on the status of Work Packages, including their performance in terms of cost. The other options do not focus specifically on cost performance: the Configuration Item Record tracks configuration items, the Quality Register monitors quality metrics, and the Highlight Report summarizes project progress without specific cost analysis.