PRINCE2 Foundation — Question 229

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Answer options

Correct answer: D

Explanation

The Checkpoint Report provides detailed updates on the status of Work Packages, including their performance in terms of cost. The other options do not focus specifically on cost performance: the Configuration Item Record tracks configuration items, the Quality Register monitors quality metrics, and the Highlight Report summarizes project progress without specific cost analysis.