PRINCE2 Foundation — Question 228

Whose approval is needed to replace a Stage Plan with an Exception Plan?

Answer options

Correct answer: B

Explanation

The Project Board is responsible for making decisions regarding the project's direction, including the approval of an Exception Plan when a Stage Plan needs to be replaced. Corporate or programme management, Project Manager, and Team Manager do not have the authority to approve such changes without the Project Board's consent.