PRINCE2 Foundation — Question 227
What product defines the reporting requirements between the Project Manager and Team Manager?
Answer options
- A. Project Brief
- B. Product Description
- C. Team Plan
- D. Work Package
Correct answer: D
Explanation
The Work Package defines the specific deliverables and tasks that need to be reported on, making it essential for communication between the Project Manager and Team Manager. The Project Brief, Product Description, and Team Plan do not specifically address the reporting requirements in the same detailed manner as the Work Package does.