PRINCE2 Foundation — Question 226
Which stakeholder interest does the senior supplier represent?
Answer options
- A. Those who will use the project outputs to deliver forecasted benefits
- B. Those providing administrative services and advice during the project
- C. Those ensuring the project delivers value for money during the project
- D. Those providing maintenance and support services after project closure
Correct answer: D
Explanation
The correct answer is D because the senior supplier is responsible for ensuring that maintenance and support services are provided once the project is finished. Options A, B, and C refer to different roles and interests that do not align with the senior supplier's focus on post-project support.