PRINCE2 Foundation — Question 230

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Answer options

Correct answer: D

Explanation

The correct answer is D because all levels of management are involved in monitoring progress and addressing deviations. Options A, B, and C limit the responsibility to specific roles, which is incorrect as the mechanisms are designed for use by all management levels to ensure project objectives are met.