PRINCE2 Foundation — Question 230
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
Answer options
- A. Only corporate or programme management
- B. Only the Project Board
- C. Only the Project Manager
- D. All levels of management
Correct answer: D
Explanation
The correct answer is D because all levels of management are involved in monitoring progress and addressing deviations. Options A, B, and C limit the responsibility to specific roles, which is incorrect as the mechanisms are designed for use by all management levels to ensure project objectives are met.