PRINCE2 Foundation — Question 222
Which process is used by the project board to respond to an exception report?
Answer options
- A. Controlling a stage
- B. Managing a stage boundary
- C. Managing product delivery
- D. Directing a project
Correct answer: D
Explanation
The correct answer is D, as directing a project involves making decisions based on exception reports to steer the project effectively. The other options, while important in project management, do not specifically pertain to the board's response to exception reports.