PRINCE2 Foundation — Question 221
Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.
Answer options
- A. change authority
- B. project assurance
- C. project support
- D. senior user
Correct answer: C
Explanation
The correct answer is C, 'project support', as the project manager typically assumes this role unless it is assigned to another individual. The other options, while relevant to project management, do not fit the context of being a default role for the project manager.