PRINCE2 Foundation — Question 223
In which process is the work to be done assigned to a team manager?
Answer options
- A. Directing a project
- B. Managing a stage boundary
- C. Controlling a stage
- D. Managing product delivery
Correct answer: C
Explanation
The correct answer is C, as controlling a stage involves monitoring progress and assigning tasks to ensure the project stays on track. Options A and D refer to broader project management activities, while B focuses on the transition between stages rather than task assignment.