PRINCE2 Foundation — Question 218

Which role represents the stakeholders who will operate the project's products after the project is complete?

Answer options

Correct answer: B

Explanation

The correct answer is B, Senior user, as this role specifically represents the stakeholders that will utilize the project's products post-completion. The other options, such as Executive and Project manager, focus on oversight and management rather than direct usage of the deliverables, while Senior supplier pertains to those providing resources or services to the project.