PRINCE2 Foundation — Question 219

Which statement about time-driven controls is CORRECT?

Answer options

Correct answer: A

Explanation

The correct answer is A, as time-driven controls are specifically designed to monitor the progress of work packages and management stages. Option B is incorrect because time-driven controls do not rely on specific events but follow a schedule. Option C is wrong since time-driven controls are ongoing throughout a stage, not just produced at the end. Option D is misleading as an exception report is not a time-driven control but rather a response to deviations from the plan.