PRINCE2 Foundation — Question 217
Which is a purpose of the 'closing a project' process?
Answer options
- A. To provide the project board with information to judge the success of a stage
- B. To confirm the project has nothing more to deliver
- C. To establish mechanisms to judge whether the project is still viable
- D. To establish mechanisms for forecasting project objectives
Correct answer: B
Explanation
The correct answer, B, accurately reflects the purpose of the 'closing a project' process, which is to ensure that all project deliverables have been completed. Options A, C, and D pertain to different phases of project management and do not specifically address the objectives of closing a project.