PRINCE2 Foundation — Question 216
According to the 'continued business justification' principle, what must project benefits be aligned to?
Answer options
- A. Regular deliveries throughout the project
- B. The business objectives
- C. The direction of the project board
- D. The technology available
Correct answer: B
Explanation
The correct answer is B, as project benefits must align with the overall business objectives to ensure that the project delivers value. Options A, C, and D are incorrect because they focus on project processes or resources rather than the alignment with business goals, which is essential for justifying the project's continuation.