PRINCE2 Foundation — Question 184

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Answer options

Correct answer: C

Explanation

Creating user and supplier groups is the correct approach as it allows for better management of stakeholders from different backgrounds. The other options may either complicate the governance structure or do not directly address the need for controlling the Project Board's size.