PRINCE2 Foundation — Question 184
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Answer options
- A. Create a separate Project Board to manage the supplier elements of the project
- B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
- C. Create user and supplier groups
- D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Correct answer: C
Explanation
Creating user and supplier groups is the correct approach as it allows for better management of stakeholders from different backgrounds. The other options may either complicate the governance structure or do not directly address the need for controlling the Project Board's size.