PRINCE2 Foundation — Question 183
Which project board decision supports the 'manage by stages' principle?
Answer options
- A. Authorizing a request for change during a stage
- B. Authorizing implementation of the next delivery stage
- C. Authorizing an exception plan after an exception report
- D. Authorizing a concession following an off-specification
Correct answer: B
Explanation
The correct answer, B, directly reflects the principle of 'manage by stages' as it involves authorizing the next phase of delivery, ensuring structured progress. Options A, C, and D involve responses to changes or issues but do not directly pertain to the progression through project stages.