PRINCE2 Foundation — Question 182

Which control must be used as a minimum requirement for applying the ‘progress’ theme?

Answer options

Correct answer: B

Explanation

The correct answer is B, as tolerances are essential for managing performance and ensuring that the project stays within acceptable limits. A project plan (A), issue register (C), and highlight reports (D) are important but do not serve as the minimum control specifically required for the 'progress' theme.