Which is a minimum requirement for the ‘organization’ theme?
Answer options
- A. Project board members must delegate their project assurance responsibilities
- B. To ensure that the change authority is delegated along with a change budget
- C. To ensure that project assurance responsibilities in the role descriptions are fulfilled
- D. The project manager must carry out team manager responsibilities in small projects
Correct answer: C
Explanation
The correct answer is C because it emphasizes the importance of fulfilling project assurance responsibilities as outlined in role descriptions, which is fundamental to the organization theme. Options A, B, and D, while relevant to project management, do not specifically address the minimum requirement that is necessary for the organization theme.