Who carries out audits that are independent of the project?

Answer options

Correct answer: A

Explanation

Quality assurance is responsible for conducting audits that assess compliance and performance independently of the project team. Project Assurance, Project Support, and Project Manager are involved in the project but do not conduct independent audits.