PRINCE2 Foundation — Question 165

How many roles make up the Project Board?

Answer options

Correct answer: C

Explanation

The correct answer is C, as the Project Board is made up of three distinct roles: the Executive, the Senior User, and the Senior Supplier. Options A, B, and D are incorrect because they do not accurately reflect the number of roles within the Project Board.