PRINCE2 Foundation — Question 166
Which action should the project manager take during the ‘assessing issues’ step?
Answer options
- A. Create an exception plan for project board approval
- B. Gain project board feedback on the issue priority
- C. Consider the impact of alternative options for resolution
- D. Determine the initial priority of the issue that has been raised
Correct answer: C
Explanation
The correct answer is C, as evaluating the impact of alternative options is crucial for effective issue resolution. Options A and B focus on approval and feedback rather than assessment, while D only addresses initial prioritization without considering alternative solutions.