PRINCE2 Foundation — Question 164
Which statement about project roles is CORRECT?
Answer options
- A. Only the roles defined in PRINCE2 may be used to fulfil project responsibilities
- B. All the roles defined in PRINCE2 must be used, but other roles may be added
- C. The project board roles defined in PRINCE2 must be used, but other roles can be defined as required
- D. Any role can be defined as required, provided the responsibilities defined in PRINCE2 are fulfilled
Correct answer: D
Explanation
Option D is correct because it allows for flexibility in defining roles while ensuring that the responsibilities from PRINCE2 are maintained. Option A is incorrect as it unnecessarily restricts role definitions to only those in PRINCE2. Option B is wrong because it implies that all PRINCE2 roles must be used, which is not a requirement. Option C is also incorrect since it limits the flexibility of defining additional roles beyond the project board.