PRINCE2 Foundation — Question 164

Which statement about project roles is CORRECT?

Answer options

Correct answer: D

Explanation

Option D is correct because it allows for flexibility in defining roles while ensuring that the responsibilities from PRINCE2 are maintained. Option A is incorrect as it unnecessarily restricts role definitions to only those in PRINCE2. Option B is wrong because it implies that all PRINCE2 roles must be used, which is not a requirement. Option C is also incorrect since it limits the flexibility of defining additional roles beyond the project board.