PRINCE2 Foundation — Question 161
Which theme establishes the mechanisms to control against baselines by providing a forecast for the project’s objectives and continued viability?
Answer options
- A. Business case
- B. Plans
- C. Change
- D. Progress
Correct answer: D
Explanation
The 'Progress' theme is crucial as it helps track the project's advancement against the established baselines, ensuring that the project remains aligned with its objectives and viability. The 'Business case' focuses on the justification of the project, 'Plans' pertain to the strategies for execution, and 'Change' deals with modifications to the project scope, none of which specifically monitor the project's adherence to baselines.