PRINCE2 Foundation — Question 162
Why does the project board review the PID during an end stage assessment?
Answer options
- A. To confirm that project controls are adequate for the remainder of the project
- B. To notify the commissioning organization that the project has been authorized
- C. To review summarized progress to date and decide what to do next with the project
- D. To ensure that post project reviews of operational performance are planned
Correct answer: A
Explanation
The correct answer is A because the project board needs to ensure that the necessary controls are in place for the project's future stages. The other options focus on aspects such as informing stakeholders or reviewing past progress, which do not directly relate to the adequacy of project controls moving forward.