PRINCE2 Foundation — Question 162

Why does the project board review the PID during an end stage assessment?

Answer options

Correct answer: A

Explanation

The correct answer is A because the project board needs to ensure that the necessary controls are in place for the project's future stages. The other options focus on aspects such as informing stakeholders or reviewing past progress, which do not directly relate to the adequacy of project controls moving forward.