PRINCE2 Foundation — Question 160
Which is a purpose of the 'progress' theme?
Answer options
- A. To ensure that the change control approach is appropriate for the size of the project
- B. To ensure that themes can be applied using techniques that are appropriate to the project
- C. To ensure that responsibilities are defined for directing, managing and delivering the project
- D. To ensure that the project remains viable against its approved business case
Correct answer: D
Explanation
The correct answer, D, focuses on the importance of aligning the project's progress with the approved business case, ensuring its ongoing viability. Options A, B, and C, while relevant to project management, pertain to change control, theme application, and role definitions, respectively, which are not the primary purpose of the 'progress' theme.