PRINCE2 Foundation — Question 149
Which is a benefit of using PRINCE2?
Answer options
- A. Is a method specifically designed for technical projects
- B. Provides for the efficient and economic use of management time
- C. Includes many of the proven planning techniques, such as critical path analysis
- D. Can be used to manage both projects and programmes
Correct answer: B
Explanation
The correct answer is B because PRINCE2 is designed to optimize the use of management time through structured processes. Option A is incorrect as PRINCE2 is not limited to technical projects; it is versatile across various types. Option C is false because while PRINCE2 does offer planning guidance, it does not solely focus on specific techniques like critical path analysis. Option D is inaccurate as it suggests PRINCE2 is only for project management when it can also effectively manage programmes.