PRINCE2 Foundation — Question 148
What must be assessed throughout the project lifecycle, as a minimum requirement for applying the 'risk' theme?
Answer options
- A. Project threats and opportunities
- B. Performance of the appointed risk owners
- C. How the risk budget is used
- D. Probability impact grid
Correct answer: A
Explanation
The correct answer, A, is crucial because identifying project threats and opportunities is fundamental to managing risks effectively throughout the project lifecycle. The other options, while important in their own right, do not represent the minimum requirement necessary for applying the risk theme.