PRINCE2 Foundation — Question 147

Which theme estimates the cost of delivering the project?

Answer options

Correct answer: A

Explanation

The Business Case theme is responsible for estimating the costs of delivering a project, ensuring that financial viability is assessed. The Change theme focuses on managing changes in the project, Plans involve creating roadmaps for execution, and Progress pertains to tracking the advancement of the project, none of which directly estimate costs.