PRINCE2 Foundation — Question 146
Who should act as the communication channel between a project and corporate or programme management?
Answer options
- A. Project Board
- B. Project Assurance
- C. Project Manager
- D. Project Support
Correct answer: A
Explanation
The Project Board is responsible for overseeing the project and acts as the primary communication channel between the project team and corporate or program management. The Project Assurance role focuses on ensuring quality and compliance, while the Project Manager manages day-to-day operations. Project Support provides administrative assistance but does not serve as the main communication link.